Aged roof surface with heavy granule loss documented before shingle replacement in Chula Vista

Project case study

Architectural Shingle Roof Replacement in Chula Vista

Eastlake, Chula Vista, CA 4 working days CSLB #1094851

Roof type

Three-tab asphalt shingle, 22 years old, single layer

Duration

4 working days

Permit path

Re-roof permit pulled through the City of Chula Vista Development Services on F Street; final inspection passed first pass. Roof documentation provided for the solar installer's structural review.

The homeowner's concern

The homeowner was preparing to add solar and wanted the roof replaced first. There was no active leak, but granule loss was heavy in the gutters and several tabs had lifted along the west-facing slope after Santa Ana wind events.

What the inspection found

  • Field shingles at the end of service life — heavy granule loss and brittle tabs
  • Lifted and unsealed tabs across the west elevation from repeated wind exposure
  • Original galvanized drip edge corroded along the rear eave
  • Two attic vents undersized for the conditioned area, contributing to summer attic heat
  • Sheathing sound throughout — no replacement required beyond two small sections at the rear eave

Scope of work performed

  1. 1Full tear-off of the existing single layer down to sheathing
  2. 2Replaced two sections of deteriorated sheathing at the rear eave
  3. 3Synthetic underlayment across the field, ice-and-water membrane in valleys and at all penetrations
  4. 4New drip edge, pipe flashings, and painted valley metal
  5. 5Installed architectural cool-roof shingles with a full ridge-vent system
  6. 6Upgraded intake and exhaust ventilation ahead of the planned solar array

Materials specified

GAF Timberline HDZ architectural shingles, cool-roof rated color
GAF FeltBuster synthetic underlayment and WeatherWatch valley membrane
GAF Cobra ridge vent
26-gauge painted drip edge and valley metal

Project photos

All photos on this page were taken by our crew on this job in San Diego County.

Aged roof surface with heavy granule loss documented before shingle replacement in Chula Vista
BeforeBefore — surface documentation from the pre-tear-off inspection walk.
Corroded drip edge previously repaired with roofing tar on a Chula Vista home
BeforeBefore — corroded rear-eave edge metal that had been tarred rather than replaced.
Crew installing GAF Timberline HDZ architectural shingles on a Chula Vista home
DuringDuring — architectural shingles going on over synthetic underlayment.

Outcome

The homeowner got a new roof with a 50-year manufacturer warranty in place before the array went up, avoiding a future solar detach and reset. Improved ridge and intake ventilation lowered measured attic temperature, and the fixed-price proposal closed with zero change orders.

Services used on this project

Have a similar roof problem in Chula Vista?

We'll inspect the roof, photograph what we find, and give you a fixed-price scope in writing — at no cost and with no obligation.

CSLB #1094851 · Bonded · Insured

Free • No Obligation

Get Your San Diego Estimate

Sent directly to sales@californiafirstroofing.com — response within 15 minutes during business hours.

By submitting, you agree to receive service-related messages. Reply STOP to opt out. Msg & data rates may apply.

Visit Our Office

Find California First Roofing

9606 Tierra Grande St, San Diego, CA 92126 · (424) 777-1619

Get Directions
Loading map…